Milling and paving along KY 1943 runs from the Skin Frame Creek Bridge at milepoint 3.432 extending eastward to the US 641 intersection at milepoint 6.94, a distance of about 3.5 miles.
Paving along KY 1943 is expected to take about two or three days to complete, weather permitting. That means the road will be closed Tuesday through about Wednesday or Thursday. The contractor will work to provide access to homeowners on each side of the closure point.
Jim Smith Contracting is the prime contractor on this $413,766 group highway improvement project.
Motorists should use appropriate caution where equipment, flaggers, and construction personnel are along the roadway in close proximity to traffic flow.
- روابط التحميل والمشاهدة، الروابط المباشرة للتحميل من هنا
---------------------------------------------------------------
شاهد هذا الفيديو القصير لطريقة التحميل البسيطة من هنا
كيف تحصل على مدونة جاهزة بآلاف المواضيع والمشاركات من هنا شاهد قناة منتدى مدونات بلوجر جاهزة بألاف المواضيع والمشاركات على اليوتيوب لمزيد من الشرح من هنا رابط مدونة منتدى مدونات بلوجر جاهزة بآلاف المواضيع والمشاركات في أي وقت حــــتى لو تم حذفها من هنا شاهد صفحة منتدى مدونات بلوجر جاهزة بألاف المواضيع والمشاركات على الفيس بوك لمزيد من الشرح من هنا تعرف على ترتيب مواضيع منتدى مدونات بلوجر جاهزة بآلاف المواضيع والمشاركات (حتى لا تختلط عليك الامور) من هنا
ملاحظة هامة: كل عمليات تنزيل، رفع، وتعديل المواضيع الجاهزة تتم بطريقة آلية، ونعتذر عن اي موضوع مخالف او مخل بالحياء مرفوع بالمدونات الجاهزة بآلاف المواضيع والمشاركات، ولكم ان تقوموا بحذف هذه المواضيع والمشاركات والطريقة بسيطة وسهلة. ــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــسلامـ.
إرسال تعليق